This project included the completion of the underground storm drainage located in phase F/G of the Christina Lake Regional Project (CLRP).
SITE’s participation in this large multi-phased project included the following:
- Site preparation – the area was cleared, graded and prepared accordingly;
- Earthwork services
- Matting was supplied and installed for stability purposes;
- Construction and installation of underground pipeline infrastructure was completed.
The storm drainage system was successfully constructed and implemented to collect the water run off from the open areas of the plant site and direct the flow to the storm water pond.
Location: | Christina Lake, AB | |||
Services: |
Civil Clearing, Slashing, Logging & Mulching Pipeline |
|||
Project Value: | Over $10 million | |||
Project Timeframe: | July 2012 to March 2013 | |||
Major Quantities: | 4500 of concrete - Storm Drain Piping (300mm to 1200mm) |